FOCIL2026-07-21_038
FOCIL Breakout #038
2026-07-21 1 decision 287 transcript lines
Transcript
- Jihoon
- Jihoon
- Jihoon
- Justin Traglia
Maybe by end of August? Or is that too soon?
- Justin Traglia
DevNet 8: large public devnet, ~first week of August
Call summary
Targets
- •FOCIL devnet 8 — ~first week of August 2026 - 00:35:37
Decisions
- •CL spec release to target ~5 days before FOCIL devnet 8 (first week of August); local interop between Lodestar and Besu to follow - 00:35:21
Highlights
- Spec Updates:
- ·Open question: whether `blockHash` param in `getInclusionList` Engine API is necessary if CL/EL share the same head; needs further analysis before merging Engine API PRs - 00:09:00
- ·EL store revamp planned: signed IL storage, request-response feeding into EngineList, and replacing inclusion committee route with dependent route (consensus-specs PR #5424, #5460) - 00:18:29
- ·Paris spec question raised: initial payload requires empty transaction set — Jihoon to investigate whether this needs updating for FOCIL (IL transactions could be included from block start) - 00:20:45
- ·Request-response for ILs: intended only for proposers and builders, not attesters; spec should clarify this - 00:24:07
- Devnet Planning:
- ·Local interop tentatively planned between Lodestar and Besu on Alpha 12 ahead of FOCIL devnet - 00:33:45
- ·Next CL spec release targeted a few days before devnet 8 (~first week of August); waiting on EL store revamp to complete first - 00:35:21
- Testing Progress:
- ·Lodestar blocked on EIP-7688 changes merging to unstable before rebasing; expects to target devnet 7 - 00:07:23
- ·Besu on Glamsterdam devnet 6; last run two weeks ago was not working - 00:07:52
- ·Yochum to start adding execution tests for FOCIL this week - 00:08:33
Action Items
- •Jihoon - Resolve `blockHash` parameter necessity in `getInclusionList` Engine API before merging Engine API PRs (execution-apis PR #609) - 00:18:01
- •Jihoon - Investigate Paris spec requirement for empty initial payload; determine if FOCIL requires spec change - 00:23:29
Key decisions
CL spec release to target ~5 days before FOCIL devnet 8 (first week of August); local interop between Lodestar and Besu to follow
spec release and local interop planning