Targets
  • •bogota-devnet-2 launch — week of October 27, 2026 - 01:37:39
  • •Next ACDE — ~November 19, 2026 (4 weeks out) - 01:46:51
Decisions
  • •Hoodi Glamsterdam hard fork canceled indefinitely; no new date set - 00:50:33
  • •Mainnet Glamsterdam fork date decision deferred until full impact analysis complete - 00:47:53
  • •ACDT extended from 60 to 90 minutes going forward - 01:13:58
  • •bogota-devnet-2 scoped to EIP-8253, EIP-4758, EIP-8298, EIP-8151; launching next week with Nethermind, Geth, ethrex - 01:37:39
  • •First merged EL+CL devnet (hegota-devnet-0) targets post-DevCon; FOCIL/frames interaction discussions to begin at DevCon - 01:38:11
  • •ACDE canceled in 2 weeks (DevCon week); next ACDE in 4 weeks - 01:46:51
Highlights
  • Hegota Devnet:
    • ·bogota-devnet-2 (EL-only) to launch next week with Nethermind, Geth, ethrex; scope: EIP-8253, EIP-4758, EIP-8298 (SETCODEFROM), EIP-8151 - 01:37:39
    • ·First post-DevCon devnet will be merged hegota-devnet-0 (EL+CL); FOCIL/frames interaction to be discussed in-person at DevCon - 01:38:11
    • ·max_fee PR (EIPs/pull/12414) to be merged into bogota-devnet-2 after call if no objections raised - 01:38:40
  • Hegota Process:
    • ·ACDT extended to 90 minutes going forward - 01:14:03
    • ·Nixo's CFI priority ordering list adopted as working V1; living document, not binding - 01:17:25
    • ·CFI vs SFI semantics debated: consensus that CFI ≠ guaranteed ship; desire to raise CFI bar and have explicit 'should Ethereum do this' discussion before SFI - 01:19:49
  • Glamsterdam Security:
    • ·ChainSecurity found EIP-8037/8038 repricing allows previously-invalid txs to exploit contracts: gas refund recovery post-revert enables balance updates without ETH transfer - 00:14:11
    • ·13 major DeFi projects identified as vulnerable; responsible disclosure ongoing; some unresponsive via bug bounty channels; search was not exhaustive - 00:22:45
    • ·Key broken assumptions: gasleft() can now increase mid-call, OOG detection patterns bypassable, 1/64 retained gas now larger under higher costs - 00:21:12
    • ·Three response tiers identified: (1) on-schedule mainnet if mitigated in time, (2) delayed mainnet same spec, (3) Glamsterdam spec changes — all contingent on full impact analysis - 00:28:02
  • Fork Status And Schedule:
    • ·Hoodi hard fork canceled indefinitely; no new date set; EthPandaOps + client teams represent ~73% of Hoodi stake, rollback deemed feasible - 00:50:33
    • ·Mainnet date implicitly on hold; December 2026 fork now very unlikely; 2027 expected - 00:47:53
    • ·Blog post to go out immediately listing pre-Glamsterdam client versions; updated as new rollback releases ship; all clients encouraged to cut new releases - 00:59:09
Action Items
  • •EF / client teams - Publish blog post immediately announcing Hoodi fork cancellation; list rollback client versions; update as new releases ship - 00:59:09
  • •All EL and CL client teams - All client teams cut new releases unscheduling Hoodi fork - 01:00:53
  • •Fredrik / Francesco / Toni / Perry and security researchers - Present impact analysis findings and analysis timeline at ACDT next week - 01:01:31

Key decisions

  • Hoodi Glamsterdam hard fork canceled indefinitely; no new date set

    UnknownFork cancelled with no rescheduled date
  • Mainnet Glamsterdam fork date decision deferred until full impact analysis complete

    CFIFork date on hold pending impact analysis
  • ACDT extended from 60 to 90 minutes going forward

  • bogota-devnet-2 scoped to EIP-8253, EIP-4758, EIP-8298, EIP-8151; launching next week with Nethermind, Geth, ethrex

    bogota-devnet-2Scope defined and launch scheduled for week of Oct 27 2026
  • First merged EL+CL devnet (hegota-devnet-0) targets post-DevCon; FOCIL/frames interaction discussions to begin at DevCon

    hegota-devnet-0Post‑DevCon devnet planned, with FOCIL/frames discussion at DevCon
  • ACDE canceled in 2 weeks (DevCon week); next ACDE in 4 weeks